At the VAMC West Haven campus, a new Combined Heat and Power (Cogeneration) plant was built to produce the facility's base level of electricity, with waste heat used to supply the boiler and chiller plants.
       
      - Completion date: 2017
      
- Construction cost:  15 million USD
      
- Architect: CannonDesign